Saturday, November 10, 2012

Playing catch-up 6

Playing catch-up 6.

Thursday progress.


Redid the Elks Creek retaining wall, looks better now.


Here is Bridge 613 retaining walls added on deck 1. Work now moving to deck 1 to complete rock work.


Here is Deck 1 & 2 showing with fascia.


Deck 2 back with foreground rock wall.


Finally Deck 2 Front, ballasting underway.

Thanks Cameron

No comments:

Post a Comment