Thursday progress.

Redid the Elks Creek retaining wall, looks better now.

Here is Bridge 613 retaining walls added on deck 1. Work now moving to deck 1 to complete rock work.

Here is Deck 1 & 2 showing with fascia.

Deck 2 back with foreground rock wall.

Finally Deck 2 Front, ballasting underway.